This page contains a Flash digital edition of a book.
Valeur_subbed.qxp 27/3/09 04:51 Page 92
Two Gas Pipelines Through the Baltic Sea to Meet the Future Gas Needs of the European Union
Figure 2: Pipe-laying Process for the Nord Stream Pipelines
Courtesy of Nord Stream AG.
The Nord Stream pipeline project extends through the exclusive concentration of suspended sediments and the sedimentation
economic zone (EEZ) of five countries (Russia, Finland, Sweden, to the seabed caused by the seabed intervention works have been
Denmark and Germany). These countries are considered ‘parties of simulated using the numerical model MIKE 3 PA developed by DHI. The
origin’ in the Espoo Convention, whereas the remaining Baltic Sea modelling simulates the transport and fate of both suspended and
coastal states (Estonia, Latvia, Lithuania and Poland) are considered dissolved substances in 3D. More than 1mm of sedimentation following
‘other affected parties’, as the project may affect these countries. As trenching of, in total, approximately 131km of pipeline will cover an
part of the Espoo process, a number of working group meetings area of approximately 3km
2
, depending on the weather conditions. The
with representatives from all nine Baltic Sea coastal states have been area where a sediment concentration greater than 10mg/l will occur
held, and comments from authorities and other stakeholders have (this is roughly the concentration that has an impact on the eyesight of
been received and included in the optimisation of the environmental diving birds and on the aesthetic quality of bathing water) is calculated
performance of the pipeline project. to be approximately 120km
2
, again depending on the weather
conditions. However, this impact is very short-term (hours), as the
Environmental Impact of the Project sediments eventually settle to the seabed within a few hundred metres
Most of the Nord Stream pipeline will be laid directly on the seabed. of the trenching and rock-dumping areas. Sediments that settle in
The presence of the pipelines, each with a diameter of 1.4m, will exposed shallow-water areas are re-suspended during rough weather
change the near-bottom current pattern near the pipelines. The conditions, finally ending up in net accumulation areas.
Swedish Meteorological and Hydrological Institute has carried out an
analysis of the impact on the hydrography and the water quality caused In general, marine benthic invertebrates are unlikely to be adversely
by the presence of the Nord Stream pipelines. Its analysis shows that affected by increased turbidity (light attenuation and scattering caused
the mixing of new deepwater flowing into the Baltic Sea might increase by suspended particles in the water column). Experience from other
by at most 2%. Increased mixing of new deepwater means lower pipeline projects shows that the impact on benthic invertebrate
salinity, increased flow rate and increased transport of oxygen, which communities and estuarine birds is limited in both time and space.
12
would tend to improve the oxygen conditions in and below the
halocline and thereby increase the deposition of phosphorus in the Earth-intervention works in the deeper parts of the Baltic Sea will
deepwater. Although the effect is very small, the pipelines may thus have a considerably smaller impact on water quality in the photic
tend to decrease the effects of eutrophication in the Baltic Sea.
11
zone than intervention works at shallower depths. In addition to the
larger dilution effects at greater depths, the presence of a pycnocline
As a consequence of dredging, trenching, backfilling, rock-dumping (a horizontal layer separating water masses of different densities
and pipeline layout in connection with the construction of the Nord because of different salinity and/or different temperature) effectively
Stream pipelines, sediments and associated substances will be prevents re-suspended sediments from reaching the surface layer.
mobilised. The sediment spreading from construction works will The release of nutrients as a consequence of the marine earthworks for
be most intense closest to the landfall sites in Russia and Germany. The installation of both pipelines has been estimated to be approximately
92
EXPLORATION & PRODUCTION – VOLUME 7 ISSUE 1
Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156
Produced with Yudu - www.yudu.com