This page contains a Flash digital edition of a book.
Eiksund_edit.1_Outsourcing_book_temp.qxd 02/11/2009 11:42 Page 108
Ormen Lange Pipelines – Geotechnical Challenges
Figure 4: Large Common Rock Support for Three
system (PLS) loading conditions. The deformation accumulation during
Large-diameter Pipelines
earthquake loading was estimated using the empirical methods
proposed by Wong
2
and Richard and Elms;
3
the calculation procedure
used is presented in more detailed by Eiksund et al.
4
Import and
Stability Analysis
export pipelines
The slope stability of rock supports is mainly calculated using the
slope stability program SLIDE.
5
Design of counterfills is an iterative
400m
process based on experience with trial and error to find the optimal
50,000m
3 length and thickness. The goal is to find a stable solution with
minimum use of rock. The stability is checked for many different
failure surfaces. In case a counterfill is required, the dimensions are
determined on basis of the three failure modes shown in Figure 3.
The local failure mode (1) determines the thickness of the counterfill,
the global failure mode (2) determines the length of the counterfill
and the local failure mode (3) defines the end stability of the
counterfill and maximum edge height.
Figure 5: Example of Complicated Rock Fill Geometry in Bjørnsundet
Examples of Geotechnical Design Tasks
An extensive soil investigation programme provided regional data, and
a selection of site-specific investigations covered many local variations.
Sub-bottom profiling was performed along the entire pipeline route
and combined with cone penetration tests and laboratory tests on soil
samples. On this basis design parameters for the soil properties were
established for the entire routes.
An extensive soil investigation
programme provided regional
data, and a selection of
site-specific investigations
covered many local variations.
In spite of the comprehensive soil investigation programme, additional
Figure 6: A Large Rock Support with Counterfill in the
soil investigations were found to be required in cases where soft clay
Storegga Escarpment under sand was not discovered by seismic investigations.
Nyhamna Landfall
On the relatively steep slope outside Nyhamna, the seabed consists of
sand or very soft clay. The large-diameter pipelines span the lower part
of the slope, extending into horizontal curves. To enable pipe lay in the
curve at the bottom of the landfall slope, a 400m-long continuous rock
support needed to be installed, as shown in Figure 4. The volume of
this support, including counterfill, was approximately 50,000m
3
. An
extensive soil investigation programme was performed to reveal
possible pockets with soft clay under the sand.
Nearshore (Bjørnsundet)
In Bjørnsundet all of the pipelines are placed together in a very narrow
valley. To fulfil the required minimum pipeline spacing for installation
feasibility and global buckling during operation, it was necessary to lift
the pipelines from the seabed onto several rock supports. An example
of this is shown in Figure 5.
EXPLORATION & PRODUCTION – VOLUME 7 ISSUE 2
108
Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148  |  Page 149  |  Page 150  |  Page 151  |  Page 152  |  Page 153  |  Page 154  |  Page 155  |  Page 156  |  Page 157  |  Page 158  |  Page 159  |  Page 160  |  Page 161  |  Page 162  |  Page 163  |  Page 164
Produced with Yudu - www.yudu.com