This page contains a Flash digital edition of a book.
Development of a Failure Detection System for Flexible Risers

Figure 2: FLEXASSURE System Operating Diagram

information to protect the asset from further damage or potential loss of the riser system.

Sub-system 4 – Detailed Data Analysis and Reporting

The data recorded on the vessel are stored in a database for each riser. These data can be sent onshore for detailed post-processing.

Laboratory Test Description

Sequences of tests were carried out in the Submarine Technology Laboratory (LTS) at the Federal University of Rio de Janeiro (UFRJ). The objectives of the tests were to determine the effectiveness of several sensor packages to consistently detect the successive failure of armour wires. The test set-up and sensors used are described below.

The flexible riser test piece is a typical 6-inch flexible riser approximately 4.3m in length, terminated with a connector at each end, as shown in Figure 3. The internal diameter of the flexible pipe is 5.9 inches.

Figure 3: Flexible Riser Tension Test Apparatus

Connector A

Tension

Connector B

The flexible riser contains a total of 144 armour wires, of which 73 make up the outer layer of wires and 71 the inner layer. The pitch of the wires is 30º, and each layer is wound in the opposite direction to the other, as shown in Figure 4. The thickness of each armour wire is approximately 2.6mm.

Flexible riser Fully fixed end Simple support Exposed wires

The test rig consists of a steel structure with two load frame assemblies equipped with hydraulic actuators to tension the flexible pipe. Tension in the test piece is carefully controlled by a computerised data acquisition and closed-loop control system.

Figure 4: Flexible Riser Armour Wires

External coating Connector A

Tension

Connector B 30º

During the flexible riser failure test, the riser pipe is installed in a horizontal position and a section of riser coating close to the fixed end is removed to expose the armour wires (see Figure 5A). Connector A is simply supported at the point where the tension is applied, and the opposite end of the riser is fully fixed.

Flexible riser Fully fixed end Simple support Exposed wires

After the tensioning system has been calibrated and the monitoring devices installed, the following test methodology is applied for the laboratory test:

Outer armour wire layer

Figure 5: Onshore Test Sequence

AB

Inner armour wire layer

• The nominal tension load applied is 80 metric tons. This represents normal operating conditions and is approximately 30% of the breaking strength.

• Both static and cyclic tension loads are applied from 40 to 80 metric tons. For some cases the maximum tension load is increased to 100 metric tons.

• The outer and inner armour wires are cut by hand using a handheld rotary tool fitted with a cutting wheel. The wires are cut to a depth of approximately 2.0mm (see Figure 5B).

• The riser is placed under increasing tensile load until the wire fails. • As soon as the wire fails, all tensile loadings are suspended (see Figures 5C and 5D).

C D

• A square cut-out is made in the external coating 70mm from the region where the wires are cut. Tensions are measured in the wires in this region to verify whether the external coating has any effect on the dissipation of wire tension after breakage.

This procedure is repeated for a total of 30 wires, 27 located at the external armour wire layer and three located at the inner armour wire

62

EXPLORATION & PRODUCTION – VOLUME 8 ISSUE 1 Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124  |  Page 125  |  Page 126  |  Page 127  |  Page 128  |  Page 129  |  Page 130  |  Page 131  |  Page 132  |  Page 133  |  Page 134  |  Page 135  |  Page 136  |  Page 137  |  Page 138  |  Page 139  |  Page 140  |  Page 141  |  Page 142  |  Page 143  |  Page 144  |  Page 145  |  Page 146  |  Page 147  |  Page 148
Produced with Yudu - www.yudu.com