This page contains a Flash digital edition of a book.
Integration of the Banking Sector into the Offshore Wind Industry Figure 1: Major Challenges for the Offshore Wind Industry


Supply chain needs to be enabled to avoid a shortage of components and large-capacity wind turbines.


Existing grids need to be extended closer to the offshore wind development zones; offshore supergrids need to be constructed.


Applicattion process, often taking several years to complete, has to become straightforward.


Supporting infrastructure for the offshore wind industry needs a boost – ports, installation vessels, etc.


Risk profile of the industry has to become lower Source: Frost & Sullivan. Long-distance Grid Connection


community at large remains largely unfamiliar with offshore wind and continues to perceive it as a highly risky sector. There are a few leaders in the banking community, notably Dexia and Rabobank, which were involved in early transactions and had developed a thorough understanding of the sector and associated risks by the end of 2008. Table 2 lists commercial banks and their current roles in the offshore wind industry. The major risks that have made banks cautious about offshore wind industry include:


• high capital costs and a need for stronger support; • long-distance grid connection;


• complexity of projects and associated construction risk; and • technology risk and long-term uncertainty about O&M costs.


The cost of a long-distance connection to the grid has become a major obstacle as it increases the project costs significantly. Connection concerns are increasingly being resolved by passing on the obligation to a network operator.


There are a number of pan-European strategic initiatives to develop several offshore supergrid projects that will enable offshore wind development. A few examples include:





The NorGer project, a first transmission line between Germany and Norway with a capacity of 1,400GW. A consortium of the Norwegian utilities Agder Energi and Lyse Produksjon and the Swiss company Elektrizitäts-Gesellschaft Laufenburg is now


There is a


number of major challenges capping the offshore wind industry growth rates; however, they are being addressed by wind turbine manufacturers, project developers, and governments at various levels.


High Capital Costs and the Need for Stronger Support Offshore wind capital costs are still higher than those for onshore wind. The regulatory framework that supports onshore wind is usually not sufficient to support this additional cost. Lately, there have been encouraging developments in regulations supporting offshore wind in several major European countries. For example, the UK has one of the biggest offshore wind markets with by far the largest potential. Here, the extension of renewables obligation certificates and introduction of renewable energy certificate banding in 2009 were of great importance in providing lenders with the stability they need to develop offshore wind projects. However, it remains to be seen how the new government will take financial incentive schemes forward.


 


 


  





 


  


                                              





 


 


   





Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124
Produced with Yudu - www.yudu.com