This page contains a Flash digital edition of a book.
Protecting Your Assets Against Corrosion and Environmental Attack


Table 1: Physical Characteristics of Available Secutec® Ultra-high-performance Grouts


Physical Characteristics


Compressive strength, fc


Tensile strength, MPa 10 ft


Static modulus GPa 70


of elasticity, Ec Dynamic modulus GPa 88


of elasticity, Ed


solution is arrived at by a carefully balanced assessment of the relative importance of these factors.


Installation costs are often the major element in the overall cost of the repair, and hence must always be minimised. Furthermore, it is possible to adopt approaches to the structural design, where there is a trade-off between the engineering efforts required and the final cost of the repair. Options include: design for full member capacity, design for full member loads, and load-sharing design. For ‘fast-track’ projects, one of the first two options may be adopted but where the project schedule permits, the load-sharing design approach would usually provide the most economical overall solution.


Execution


ULO Systems LLC adopt a staged approach to the development of a repair scheme from assessment, and design through to installation. To illustrate how this is implemented a summary overview of different strengthening projects follows.


1. At a platform. The conductor guide frame had suffered severe fatigue damage from the effects of wave slam and vertical wave load component, which caused cracks in the frame members where they met the jacket’s main horizontal tubular members. The design took account of the interplay between the original structure and the clamps placed upon it. By increasing the stiffness of certain of the horizontal stressed grouted clamps it was possible to reduce the loads attracted to other nodes sufficiently to avoid the need to place clamps around them.


2. During a routine underwater inspection of a platform, cracking in some of the welds connecting five brace members to the node joint were determined. The repair took the form of a 3D framework surrounding the node that was connected to the adjacent braces or the node using stressed grouted clamps. The new brace members of the framework were shop welded to the clamps or where site connections were necessary, a conventional pile/sleeve type connection was used taking advantage of weld bead shear connectors, selected to provide the maximum tolerance on final positioning and thereby facilitate installation and subsequent grouting.


3. A routine structural analysis to a platform found it was necessary to strengthen the jacket structure at a particular node connecting one of the legs to a diagonal brace. The analysis concluded that strengthening would be best achieved by installing grouted,


42 8 65 77 7 55 60 5 35 37


Unit Secutec Secutec Secutec Secutec B-4


28-day MPa 210


B-1 170


S-3 130 S-1 110


mechanical clamps around the node, temporarily secured using spacer bolts. Specially constructed seals were installed at the open ends of the clamp and, when activated, sealed the clamp annulus prior to filling with a high performance grout. When the grout had gained strength, the spacer bolts were withdrawn and post-stress applied to the clamp by means of the external stressing bolts.


4. At two different platform locations, strengthening was required to the main legs and for different reasons. At the first, while the original design was main piles with welded crown shims at the top of the jacket, shortly after installation, the structure developed a ‘shimmy’ or, ‘wobble’. To overcome this and increase the leg stiffness, the solution implemented was to pressure grout the annulus with high-performance cement. At the second location it was necessary to strengthen the legs to permit elevation of the deck. The leg-strengthening scheme incorporated external sleeving with a small annulus for subsequent grouting. Due to the large volume of infill material needed for the legs, a specialised low-heat cement grout was to minimise heat of hydration. Grout filling the legs provided increased resistance to buckling and also resistance to the post tensioning forces developed by the clamp (sleeve) bolts and improved ultimate load capacity.


Ultra-high-performance Grouts


More recently, ULO Systems LLC in association with Contec ApS with have identified the Secutec® range of ultra-high-performance grouts (UHPGs) that may be used to enhance the integrity of structures. The UHPGs have exceptional properties with E-modulus that exceed 70GPa (10,000ksi) and compressive strengths that exceed 210MPa (30,400psi).


These physical characteristics are particularly beneficial when undertaking structural upgrades, because the UHPG may be injected into members, nodal joints or split sleeves, etc. to reinforce and enhance the integrity of the structure. In particular, because of the exceptional mechanical properties of the UHPGs it is possible to undertake repairs to caissons or piling using fibreglass sleeves or moulds because the high bond and shear strength of the UHPG will provide excellent bond and shear distribution, often eliminating the need for heavy steel clamps.


Other remedial areas where the UHPGs may be applied include corrosion protection and blast wall and firewall strengthening.


In addition, the UHPGs are utilised in the renewables/wind turbine market where the high E-modulus ensures good load transfer and the increased connection stiffness reduces the natural period or frequency of monopile structure, which, because of their ‘flexibility’, is often a problem.


The principle physical characteristics of the Secutec® materials are summarised in Table 1.


The properties and characteristics of the Secutec materials have been tested by many professionally accredited bodies and noteworthy institutions that include, The Delft University of Technology


EXPLORATION & PRODUCTION – VOLUME 8 ISSUE 2


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108