Deepwater Field Development and Concept Selection


Table 1: Comparison of the Existing Floating Platforms Spar


TLP Variants Scalability Classic, truss and cell


Functionality Dry/wet trees; surface BOP drilling, Dry/wet trees, surface BOP drilling, completion, intervention


completion, intervention constraints and increased depth; large payloads (about 5,000ft)


Installation, High degree of complexity, cost integration, and schedule risk commissioning Flexibility


Limited for decommissioning, relocation, expansion


Relatively complex


Limited for decommissioning, relocation, expansion


BOP = blow-out preventer; HP = high pressure; SCR = steel catenary riser; TLP = tension leg platform.


and will significantly increase platform size and capital expenditure (CAPEX). This has to be traded off against increased ultimate recovery. In some deep subsalt reservoirs, boosting may be a necessity.


Proven Deepwater Floating Platforms


Currently, there are four major categories of floating platform available (see Figure 4). Semi- and floating production storage and offloading (FPSO) platforms were introduced in the late 1970s and converted from drilling rigs and oil tankers. They have since evolved into purpose-built hulls capable of supporting massive payloads in very deep and harsh environments. Tension leg platforms (TLPs) and spars were introduced in the 1980s and 1990s in response to the need for dry trees and direct well access. All spars and TLPs are purpose-built hulls. They provide the flexibility of drilling, completion, production and intervention; however, the cost of carrying a full drilling rig burdens the floating platform enormously.


Table 2: Early Decisions on Key Platform Functions


Reservoir Characteristic Drill Centres Wet or Dry Tree Drilling, Workover Development or Production Rig


Small Medium, stacked


or compact Large, stacked


Single Single


Single


or compact Large, areally extensive Multiple Multiple, sub-economic Multiple


Wet Dry


Dry


Wet Wet


Production Workover


Drilling


Production Production


Each category has multiple configurations that have evolved to provide a greater range of functional capabilities and cost-effectiveness (see Table 1). As Table 1 shows, there is no single solution that is superior to all others in every category. Each of these platforms can be used in a specific case if the situation demands it. In addition to the proven platform


Relatively simple


Semisubmersible Classic, extended, MOSES and Sea-star Conventional and deep-draft


Dry/wet trees, surface BOP drilling, completion, intervention


Dual barrier production riser HP Water depth by tendons and payload Limited envelope of SCR applicability


Shipshape


Spread moored, turret moored Wet tree, subsea BOP drilling possible, integrated oil storage Tower or wave risers


required for deeper waters, accommodate very large topsides


Simplest integration,


commissioning, wet (or dry) tow from yard to site


Relatively simple decommissioning, Simplest to expand topsides, relocation, expansion


relocate or decommission


TEAM PROJECT S.R.L. is a young and dynamic group, established in 1999 as a multidiscipline engineering service company within the on and off shore sectors. The potential of TEAM PROJECT S.R.L. lies in its highly qualified, multidisciplinary teams of engineers and technicians.


Starting from conceptual studies to detailed engineering, TEAM PROJECT S.R.L. can provide to EPC contractors a complete design service for construction and maintenance of a wide range of plants and systems in the following fields:


• Oil & Gas • Fire Fighting • R&D for standard products


Thanks to the great experience over the years and the attention to details, TEAM PROJECT S.R.L. has always been recognised as a highly experienced company in creating innovative and cost-effective solutions.


Design Quality and service delivery have always been a TEAM PROJECT S.R.L. priority: all provided design processes are governed by a Project Quality Plan complying with the requirements of ISO 9001, applicable codes, standards, guidelines and the needs of plant operations and maintenance.


Among the primary services we offer it is possible to find: • project management • feasibility studies • basic & detail engineering • modularization studies (i.e. PAU, PAR, etc.) • 3D plant modelling • lay-out of plant & machinery • equipment & piping design • stress analysis for piping & structures • hydraulic calculation • CFD • multi-physic analysis & simulation • installation & connection details • electrical & instrumentation • handbooks & procedures


All projects are supported by the use of specific software packages.


Our mission can be summarized as to get it right first time, striving for maximum efficiency at the lowest cost.


TEAM PROJECT S.R.L., Via Villoresi, 68, 20010 Vittuone (MI), Italy. Tel: +39 2 90310098 Fax: +39 2 90311132 Email: info@teamproject.it Website: www.teamproject.it


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108