Identifying Major Accident Hazards and Containing Hydrocarbons by Utilising Operational Knowledge Figure 1: Comparison Between Different Types of Safety
Process safety
Major accident hazards
Personal safety
Slips, trips and falls
Table 1: Process Hazard Review Guidewords
Internal explosion Reaction
Extreme pressure Extreme temperature Puncture
Excess loading
Long-term weakening Overfill Opening Leak
Figure 3: Missing Lock on Isolation Valve Increasing the Isolation Risk
Very unlikely
Possible Figure 2: The Need for Periodic Process Safety Reviews Continuous improvement
Process safety
performance Initial
learning phase
Changes in personnel Loss of knowledge Ageing equipment ‘Creeping’ change
Life of plant
safeguards. The experience of the team is used to identify current weaknesses, for example a level sensor on a safety-critical trip system that is known to regularly fail.
Recommendations for improvements are raised that are focused towards major accident hazards and known problem areas. These fall into the following generic categories, with a bias towards procedural changes rather than costly hardware changes:
• • • • •
Simple risk-reduction measures, e.g. fitting blank flanges to drain valves on hazardous lines.
Improvements to operating or maintenance procedures to ensure best practices are followed.
Improved inspection and testing of safety-critical equipment, e.g. vent lines on storage tanks liable to blockage.
New layers of protection for high-risk events to meet current company or international standards.
Research into poorly understood hazards, such as static control measures, or consequence modelling to determine the extent and severity of fires, explosions or toxic releases.
Plant tours are regularly made by the team leader accompanied by an experienced operator. This provides an opportunity to check the condition of safety-critical equipment in the field and confirm the status of measures stated at the team meetings. For example, a manual valve on the inlet line to an low pressure gas/condensate separator vessel was specified to be ‘locked open’ to prevent the
88
upstream line from being over-pressured and rupturing. It was found that the lock was missing from the valve, as shown in Figure 3, increasing the risk of the line being isolated in error. Most companies have a process safety risk matrix similar to the example in Figure 4. All of the identified events are located on the matrix using suitable word models and the judgement of the team guided by an experienced leader. The completed matrix showing the number of events at each risk level is a powerful toolto show the areas of concern. It allows for prioritisation of recommendations for improvements.
Implementing Improvements
Completing the PHR is the first stage of the improvement process and it is essential that the recommendations raised are then addressed promptly. Simple low-cost improvements should be implemented at the earliest opportunity to reduce risks and show a commitment to the improvement process. Technical assessments are then required to identify practical improvement options and carry out cost–benefit analyses. These are required to convert the recommendations into a series of specific actions with owners and completion dates.
The cost of making changes to an operational facility is higher than the cost of those made during the initial design stage. A common problem is making decisions on expenditure where the benefits are limited to reducing risks with no financial benefits. Events judged to be at high risk require urgent attention and changes to reduce such a risk should be made regardless of cost.
HYDROCARBON WORLD – VOLUME 5 ISSUE 2
Constant risk
Page 1 |
Page 2 |
Page 3 |
Page 4 |
Page 5 |
Page 6 |
Page 7 |
Page 8 |
Page 9 |
Page 10 |
Page 11 |
Page 12 |
Page 13 |
Page 14 |
Page 15 |
Page 16 |
Page 17 |
Page 18 |
Page 19 |
Page 20 |
Page 21 |
Page 22 |
Page 23 |
Page 24 |
Page 25 |
Page 26 |
Page 27 |
Page 28 |
Page 29 |
Page 30 |
Page 31 |
Page 32 |
Page 33 |
Page 34 |
Page 35 |
Page 36 |
Page 37 |
Page 38 |
Page 39 |
Page 40 |
Page 41 |
Page 42 |
Page 43 |
Page 44 |
Page 45 |
Page 46 |
Page 47 |
Page 48 |
Page 49 |
Page 50 |
Page 51 |
Page 52 |
Page 53 |
Page 54 |
Page 55 |
Page 56 |
Page 57 |
Page 58 |
Page 59 |
Page 60 |
Page 61 |
Page 62 |
Page 63 |
Page 64 |
Page 65 |
Page 66 |
Page 67 |
Page 68 |
Page 69 |
Page 70 |
Page 71 |
Page 72 |
Page 73 |
Page 74 |
Page 75 |
Page 76 |
Page 77 |
Page 78 |
Page 79 |
Page 80 |
Page 81 |
Page 82 |
Page 83 |
Page 84 |
Page 85 |
Page 86 |
Page 87 |
Page 88 |
Page 89 |
Page 90 |
Page 91 |
Page 92 |
Page 93 |
Page 94 |
Page 95 |
Page 96 |
Page 97 |
Page 98 |
Page 99 |
Page 100