This page contains a Flash digital edition of a book.
Atlas Copco Rental UK Commences Its Largest Single Offshore Project a report by Atlas Copco Rental


Dundee, Scotland, late May 2011. Atlas Copco Rental was commissioned to commence an in-house test run and feasibility overview involving 25,000 scfm of primary air, nitrogen membranes and boosters. This comprehensive engineered rental package involved up to 22 high-pressure compressors, five nitrogen membrane units, four compressor boosters and two 500 kVA gensets, along with ancillaries and engineered peripherals.


The task was in preparation for a project to dewater and pig an 80 km long, 26 inch diameter subsea gas pipeline in the Norwegian offshore sector, where the work would be carried out from a dedicated support vessel.


With successful completion of the onshore trials, and all risk assessments complete, the packed air spread was approved by Subsea 7 and prepared for shipment.


On target to commence production of gas and oil in the latter half of 2011, the Norwegian BP Skarv project is thought to be one of BP and its partner’s most northerly offshore developments. Comprising a subsea system of 16 wells on five templates, the new development will feed gas to an 80-kilometre (50-mile) subsea spur line. This will link into Norway’s existing Aasgard pipeline, with the gas making its way to consumers in Germany.


The lead role in the process was undertaken by offshore test specialists IKM Testing of Norway.


A key part of the dewatering and drying process is to drive a train of six dewatering pigs through the pipe and it is here where


Precise pressure and flow control is vital, any fluctuations being liable to impact upon the speed and efficacy of the pig train.


The first challenge for Atlas Copco Rental, however, was to assemble all the equipment required to meet the demands of the project in the short lead time required by the client.


Over a period of six weeks, equipment was sourced from key Atlas Copco Rental outlets throughout Europe and Asia, with the


The first challenge for Atlas Copco Rental was to assemble all the equipment required to meet the demands of the project in the short lead time required by the client.


complete equipment spread assembled and readied for dry-land testing in Dundee, Scotland. Once everything was checked and tested over a multiple hour ‘simulated running’, the 400-ton equipment spread was later decommissioned and loaded onto the cargo/transit ship which was berthed in Dundee awaiting load out (see Figure 1).


From the outset, everyone's object and key priority was SAFETY FIRST.


The customers’ representatives were on-site for over eight days whilst the simulation and function tests took place at Atlas Copco Rental.


The Norwegian BP Skarv project is thought to be one of BP and its partner’s most northerly offshore developments.


Atlas Copco Rental Oil & Gas has been called in, our remit being to provide sufficient air/nitrogen volume pressure and quantity to drive the pig train through the pipeline, whilst meeting the site additional criteria.


Inert nitrogen was selected to propel the pig train through this gas line, primarily as it is a safer process and is proven to assist in the pipeline drying process.


50


This maintained effective communication and ensured expectations at every stage were achieved by all stakeholders.


Finally, after successful completion and recording of the spread’s performance, the customer signed acceptance documentation and the mobilisation to site was initiated.


Fast forward to June, and the complete equipment spread was transferred from the transit vessel to Subsea 7's specialist reel-lay vessel Seven Oceans, which was berthed in Stavanger.


After full function testing on board the vessel in Dusavik, Stavanger, the Seven Oceans started transit to the Skarv field and was rigged up and readied to supply pressurised nitrogen. Filled with treated seawater, the subsea pipeline was now ready for dewatering prior to its commissioning.


© TOUCH BRIEFINGS 2011


Subsea and Pipeline


Page 1  |  Page 2  |  Page 3  |  Page 4  |  Page 5  |  Page 6  |  Page 7  |  Page 8  |  Page 9  |  Page 10  |  Page 11  |  Page 12  |  Page 13  |  Page 14  |  Page 15  |  Page 16  |  Page 17  |  Page 18  |  Page 19  |  Page 20  |  Page 21  |  Page 22  |  Page 23  |  Page 24  |  Page 25  |  Page 26  |  Page 27  |  Page 28  |  Page 29  |  Page 30  |  Page 31  |  Page 32  |  Page 33  |  Page 34  |  Page 35  |  Page 36  |  Page 37  |  Page 38  |  Page 39  |  Page 40  |  Page 41  |  Page 42  |  Page 43  |  Page 44  |  Page 45  |  Page 46  |  Page 47  |  Page 48  |  Page 49  |  Page 50  |  Page 51  |  Page 52  |  Page 53  |  Page 54  |  Page 55  |  Page 56  |  Page 57  |  Page 58  |  Page 59  |  Page 60  |  Page 61  |  Page 62  |  Page 63  |  Page 64  |  Page 65  |  Page 66  |  Page 67  |  Page 68  |  Page 69  |  Page 70  |  Page 71  |  Page 72  |  Page 73  |  Page 74  |  Page 75  |  Page 76  |  Page 77  |  Page 78  |  Page 79  |  Page 80  |  Page 81  |  Page 82  |  Page 83  |  Page 84  |  Page 85  |  Page 86  |  Page 87  |  Page 88  |  Page 89  |  Page 90  |  Page 91  |  Page 92  |  Page 93  |  Page 94  |  Page 95  |  Page 96  |  Page 97  |  Page 98  |  Page 99  |  Page 100  |  Page 101  |  Page 102  |  Page 103  |  Page 104  |  Page 105  |  Page 106  |  Page 107  |  Page 108  |  Page 109  |  Page 110  |  Page 111  |  Page 112  |  Page 113  |  Page 114  |  Page 115  |  Page 116  |  Page 117  |  Page 118  |  Page 119  |  Page 120  |  Page 121  |  Page 122  |  Page 123  |  Page 124